(KAIR)--The Kansas Department of Transportation has announced that the next phase of the U.S. 73/K-7 road reconstruction project in Leavenworth has started.
According to a release from KDOT, phase seven of the project started Monday, one day ahead of schedule. During this phase, eastbound and southbound U.S. 73/K-7 from 16th Street to Tenth Street will be reduced to one lane in each direction with no access from the side roads.
Phase seven is tentatively scheduled to be completed in mid October, weather permitting.
Phase eight, which covers Tenth Street to Seventh Street, is tentatively scheduled to start on September 14th.
© Many Signals Communications
MOST VIEWED STORIES
Holton woman killed in Jackson Co car-deer accident
Revised flood predictions along the MO River
Valuation change notices coming soon for Nebraska residents
Lancaster shooting, threats, land man in jail
Case dismissed in charity fraud allegations
Three injured in Thursday Jeff Co collision
Atchison Police probe car wash thefts
KHP pursuit ends in Jackson Co
Jeff Co North USD 339 bond issue defeated
Atchison Co's Laurie seeks another term as Sheriff
Atchison's Amelia fireworks voted 3rd in nation
USD 415 board holds special meeting
Former KS AG files for Congress
One injured in Jeff Co collision
Atchison Co vets to honor comrades Monday
Brown Co Commissioner files for re-election
Falls City Hot Air Balloon Festival coming in June
LATEST STORIES
Plans underway for " No Summer Hunger" program
Whiting woman sentenced in theft of fire dept. funds
HCC hires new Vice President for Academic Affairs
One injured in Jeff Co collision
Holton woman killed in Jackson Co car-deer accident
Atchison Co vets to honor comrades Monday
Richardson County Board receives organization updates