(KLZA)-- Work continues on Highway 136 through Auburn. Paving of the driving surfaces on phase 3, from K Street to Irvin Drive was completed this week. Work to prepare intersections and drives in that section is ongoing and if the weather cooperates cement should be poured in at least part of the intersections on Saturday.
Sidewalks in the area should be completed by mid-July.
Phase 2, which is H Street to F Street, was opened to local traffic on Tuesday. Truck and Semi-traffic should still be using the detours around the area.
Some of the sidewalk will be removed and replaced in downtown Auburn between K and H Streets. This will be to correct an issue with rain- water flow.
© Many Signals Communications
MOST VIEWED STORIES
St. Joseph Mo man killed in KS crash
Sunday evening kitchen fires battled in Atchison; one injured
Atchison man arrested following pursuit
Hiawatha USD 415 Supt. announces retirement
Woman arrested after Holton search warrant
Packed hearing Thurs for Atchison Co Lake's future
Officer bitten during Atchison arrest
Pottawatomie Co Sheriff's Office K9 dies
City Commission approves removal of breed-specific dog ban
New Jeff Co North leadership hired
Local judge among 15 seeking Supreme Court vacancy
Longtme Falls City business owner dies
"Highly anticipated" blackout plates coming to KS
New Brown Co Special Education director hired
Falls City Council takes action on vacant properties
County Commission approves bid for new landfill building
Plea entered in Jackson Co child sex case
LATEST STORIES
Click It or Ticket campaign begins May 18
Boil Water Advisory Rescinded for Robinson
Pawnee City School Board meets
Johnson-Brock School Board meets
Packed hearing Thurs for Atchison Co Lake's future
Plea entered in Jackson Co child sex case
Doniphan Co to reapply for grant for ADA project