Work resumed this week on the Seneca Main Street reconstruction project.
The nearly $1.6 million project calls for the reconstruction of three blocks of the city’s brick Main Street from 3rd to 6th Streets, along with new concrete sidewalks, curbs and gutters. Seventy-five percent of the project cost is being funded by a grant through the Kansas Department of Transportation.
Work began on the project last August and was halted by mid-November so the construction didn’t interfere with downtown merchants during the holiday season.
Main Street businesses were presented last week with a revised construction schedule.
City Administrator Tammi Haverkamp says efforts are focused on completing the work as quickly as possible with the least amount of inconvenience to business owners and the community ( play audio )
Depending on the weather, the project is projected to be completed by June 1st.
Bryant and Bryant Construction of Halstead is the primary contractor on the project.
MOST VIEWED STORIES
Two arrested after Doniphan Co traffic stop
Seven arrested in Atchison drug investigation
Atchison man sentenced on child sex charge
Sabetha Community Hospital appoints new CEO
Two arrested after Jackson Co pursuit and manhunt
Updated: Mayetta woman now accused of attempted murder
Atchison woman sentenced on charges in fatal crash
Heavy rain contributed to wreck injuring one person
One killed, 3 injured in NW MO crash
Man arrested in Tecumseh, Neb following standoff
Longtime Sabetha Fire Chief recognized for service
Longtime Nemaha Co Appraiser retires
Jackson Co traffic stop results in two arrests
Atchison Co: Motorists reminded to use only hwy detours
Hiawatha City Commission sets fireworks dates, times
Child abuse arrest made in Pawnee County
Brown Co Appraiser re-appointed
Brownville under consideration for small modular nuclear reactor
LATEST STORIES
Atchison man facing drug-related charges in Jackson Co
Updated: Mayetta woman now accused of attempted murder
Nominees sought to fill local judicial seat
Protect yourself from West Nile Virus
Unemployment figures mixed in SE Nebraska in May
Purchase of 2 patrol units for Richardson Co Sheriff's Office approved
One killed, 3 injured in NW MO crash
New firm to do facilities assessment for USD 415