(KLZA)-- The Falls City School Board received updates on facility projects when they met Monday evening.
The High School HVAC project to do list includes demolition of the existing boilers which is tentatively scheduled to begin May 2.
The new boiler has been ordered and is in Omaha.
The new locker room air handling unit is on order and should be shipped in early July. The existing unit will be ready for demolition following the last day of school.
The turf replacement project at the football stadium is moving forward. The bid opening will be the week of March 28 and construction will begin the week of June 6 with a substantial completion date of July 13.
© Many Signals Communications
MOST VIEWED STORIES
Holton man killed in Jackson Co crash
Morrill pair arrested on drug, child endangerment charges
Horton City Clerk's resignation accepted Monday
Effingham owner regains truck following theft, arrest
Falls City man sentenced to Federal Prison
Cold case investigation leads to Holton warrant
Ground Broken for new Sac and Fox Trad'n Post
Local residents avoid injury in chain reaction crash
Jackson Co traffic stop leads to arrest
One held for past Atchison shooting
90 mph+ downburst winds blamed for Thursday damage
Wamego man sentenced in second fentanyl-related death
Mayetta pair arrested on meth, child endangerment charges
Stolen trailer, 4-wheeler, recovered in Atchison
Early Thursday storms leave damage, outages, locally
Juveniles face charges following Atchison break-in
Atchison Co's Oswald named honorary bailiff for KS Court
LATEST STORIES
Council hears report from golf course
Commission approves agreement for budget help
Pawnee City School Board approves personnel changes
Hazard mitigation planning meeting set for Atchison County MO
Effingham owner regains truck following theft, arrest
Cold case investigation leads to Holton warrant
Senator Slama on tax relief efforts
SE Nebraska March unemployment report