(KLZA)--  After beginning construction in mid-June for a deck replacement project, a Holt County bridge is now complete. 

The Missouri Department of Transportation contracted with Phillips Hardy, Inc. to replace the bridge decks on four bridges in Northwest Missouri. Crews completed the last of these bridges, Holt County Route T Easter Creek Bridge, and reopened the roadway Tuesday afternoon.
The bridges included in this deck replacement project were:
Holt County Route T bridge over Spring Branch – complete 
Atchison County Route U bridge near Phelps City – complete 
Holt County Route H bridge over Nichols creek – complete 
Holt County Route T bridge over Easter Creek near Oregon – completed. 
These bridges are included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.
 


© Many Signals Communications

You will need to be logged in to leave a comment.

Please Login


characters left

The posting of advertisements, profanity, or personal attacks is prohibited.

Click here to review our Terms of Use.