Leavenworth Road Project Delayed
05/11/2015

(KAIR)--The Kansas Department of Transportation has announced that the pavement replacement project on a 1.6 mile stretch of U.S. 73/K-7 in Leavenworth County, scheduled to start Monday has been moved to Tuesday.

According to a release from KDOT, the project will take place on a section of road between the north side of the Fourth Street/Cheyenne Street intersection to the 20th Street interchange, including a section on K-92 from Fourth Street to the Centennial Bridge.

Construction work will be completed in multiple phases, which each phase scheduled to be completed in thirty calendar days.

Work will start on the north side of U.S. 73/K-7 between the Seventh and Tenth Street intersections. It will then move west in the north side lanes to the 20th Street interchange and then will switch to the south side lanes as crews head east to Seventh Street.

Traffic on U.S. 73/K-7 will be placed side by side, and reduced to one lane in each direction twenty four hours a day through each phase of construction. Traffic will be directed through the work zone via cones and signage.
Work will take place primarily during daylight hours Monday-Friday, with some occasional Saturday work.

There will be a 35 MPH speed limit and drivers should expect delays during peak commute times.

Miles Excavating, out of Basehor, is the primary contractor on the approximately $6.8 million project, Work is scheduled to be complete by mid-December.


© Many Signals Communications

You will need to be logged in to leave a comment.

Please Login


characters left

The posting of advertisements, profanity, or personal attacks is prohibited.

Click here to review our Terms of Use.