Nebraska Public Power District Approves Increase in Production at Cooper Nuclear Station
(KLZA) A unanimous vote Friday by the Nebraska Public Power District’s Board of Directors to increase the amount of power produced at its Cooper Nuclear Station, located near Brownville, (CNS) could reinforce the utility’s already 40 percent, non-carbon emitting generation portfolio.
NPPD will seek to increase the plant’s output by 146 megawatts from its current 800-megawatt nameplate, through an extended power uprate (EPU). The increase in generation will require no additional facilities or employees. The project requires some equipment upgrades that complement investments NPPD has already made in replacing major components over the last several years.
“The 146 extra megawatts will help NPPD meet the additional load requirements we expect to have as early as 2018,” NPPD President and CEO Pat Pope explained. “Other benefits of an EPU include increasing the amount of electricity we can produce from a non-carbon producing resource, when potential greenhouse gas regulations are on the horizon. In addition, off-system sales from the facility into the regional energy market could be a significant benefit to Nebraska customers when such revenues are returned and put toward NPPD’s operational expenses.”
One of the key pieces of equipment to be replaced will be the plant’s high-pressure turbine, ordered last May due to the long, lead time in manufacturing.
The board’s approval is not a guarantee the project is a given, but it is a very good generation opportunity for NPPD to pursue,” Pope explained, noting that a thorough analysis must be conducted along with obtaining regulatory approvals. NPPD will seek Nuclear Regulatory Commission approval for a license amendment and approval from the Nebraska Power Review Board.
The project requires an estimated capital investment of $243 million dollars, $60 million of which is already committed to modifications necessary to meet relicensing requirements NPPD agreed to in 2010 when the Nuclear Regulatory Commission (NRC) renewed NPPD’s operating license, extending it to 2034.
Much of the new equipment will be installed during three, successive refueling and maintenance outages scheduled for 2014, 2016, and 2018. The new high pressure turbine is expected to be installed during the 2016 outage.
The Board approved two contracts with GE-Hitachi Nuclear Energy Americas, LLC, to provide the engineering services to perform analyses and evaluation of the nuclear steam supply system in order to make the application to NRC, at a cost of $30,547,411, and an additional $14,195,000 for the purchase of power range neutron monitoring system, a system upgrade related to the EPU project.
NPPD will continue to evaluate and then implement as necessary other generation, energy efficiency and demand side management options in accordance with the Integrated Resource Plan process.
The Cooper Nuclear Station located near Brownville is the largest employer in Southeast Nebraska.
© Many Signals Communications
MOST VIEWED STORIES
Doniphan Co search warrant leads to 3 arrests
Sex crimes charges hold Atchison teen
Fleeing, drugs, hold Atchison man
Atchison's USD 409 names new Superintendent
ATCH CO SO seeks tips regarding stolen motorcycle
Third day Superintendent candidate named by USD 409
Expansion of Atchison skatepark planned
NioCorp to begin 12-week drilling program
Olathe woman arrested in Jackson Co on drug charges
Hiawatha City Commission approves fireworks on trial basis
Jackson Heights names new MS/HS Principal
Longtime Sabetha Fire Chief to retire
Two new members appointed to Brown Co Planning Commission
Bids approved for two Doniphan Co road projects
Falls City Council hears updated on electric department
Richardson Co Courthouse rededication ceremony held
LATEST STORIES
Atchison foundry renamed in acquisition
Spring cleaning time in the city of Horton
Summer EBT cards being distributed in Nebraska
Early morning power outage planned for Falls City
MO Congressman Graves critical of USPS
Grant apps for Falls City Amphitheater project denied
Jackson Heights names new MS/HS Principal
Seatbelt surveys coming to local counties
RELATED STORIES
New GM appointed at Cooper Nuclear Station
Cooper Nuclear sirens sound due to false alarm
Local entities taking part in nuclear plant drill
Hydrogen leak repaired at Cooper Nuclear plant
Federal Regulators to Inspect Cooper Nuclear Plant
Cooper Nuclear Drill Scheduled
NPPD: No Plans To Close Cooper Nuclear Station