Power Line Application Rejected for Second Time
07/15/2016

JEFFERSON CITY, Mo. (AP) — Regulators have rejected a second application for the Missouri portion of a power line that would carry wind energy from Kansas to Indiana.

However, the Missouri Public Service Commission’s vote on Tuesday on the application from Clean Line Energy Partners cited a filing technicality and the Houston-based company plans to file another application.

Clean Line is proposing a $2.3 billion power line from Dodge City, Kansas, to a substation in Sullivan, Indiana. Its second application was rejected because the company hadn’t filed the required 60-day notice before re-filing its application.

The commission rejected the original application last year after some landowners along the line’s proposed Missouri route raised objections. Kansas, Illinois and Indiana have approved the project.

Clean Line filed a notice Tuesday that it intended to re-file its application.

 


© Associated Press

You will need to be logged in to leave a comment.

Please Login


characters left

The posting of advertisements, profanity, or personal attacks is prohibited.

Click here to review our Terms of Use.